The Project Product Description is created in the Starting up a Project process as part of the initial scoping activity and may be refined during the Initiating a Project process when creating the Project Plan.
It is subject to formal change control and should be checked at stage boundaries (during Managing a Stage Boundary) to see if any changes are required.
It is used by the Closing a Project process as part of the verification that the project has delivered what was expected of it and that the acceptance criteria have been met.
The Project Product Description includes:
The approved Project Product Description is included as a component of the Project Brief and is used to help select the project approach.
The Project Product Description defines what the customer is expecting the project to deliver and the project approach defines the solution or method to be used by the supplier to create the project product.
The Project Product Description is a special form of Product Description in that it includes the customer’s quality expectations and, at this level, the quality criteria and quality methods constitute the acceptance criteria and acceptance methods for the project overall.