The PRINCE2® approach
Prepare the schedule
Calculate total resource requirements and costs
The resource requirements can be tabulated, and the cost of the resources and other costs calculated to produce the plan’s budget.
The budget should include:
- Costs of the activities to develop and verify the specialist products, and the cost of the project management activities
- Risk budget (see the section covering ‘Risk’)
- Change budget (see the section covering ‘Change’)
- Cost tolerances.
The use of risk budgets and change budgets is optional.
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.