Issues may be raised at any time during the project, by anyone with an interest in the project or its outcome.
Below provides a summary of the different types of issue that need to be dealt with during a project.
Type | Request for change |
Definition | A proposal for a change to a baseline. |
Example | The Senior User would like to increase the capacity of a product from 100 to 150 users. |
Type | Off-specification |
Definition | Something that should be provided by the project, but currently is not (or is forecast not to be) provided. This might be a missing product or a product not meeting its specification. |
Example | Advice from a supplier that they can no longer deliver one of the products specified by the customer. |
Type | Problem/concern |
Definition | Any other issue that the Project Manager needs to resolve or escalate. |
Example | Advice from a Team Manager that a team member has been taken ill and as a result the target end date for a Work Package will slip by a week. Notification that one of the suppliers has gone bankrupt, resulting in the need to identify and engage a new supplier. |