Activities
Prepare planned closure
Before closure of the project can be recommended, the Project Manager must ensure that the expected results have all been achieved and delivered.
Diagram 1 shows the inputs to, and outputs from, this activity.
© Crown copyright 2005 Reproduced under licence from OGC


Diagram 1
PRINCE2® recommends the following actions:
- Update the Project Plan with actuals from the final stage
- Request a Product Status Account from Project Support. From the Product Status Account, ensure that the project’s products:
- Have been approved by the authorities identified in their Product Descriptions
- Meet all the quality criteria, or are covered by approved concessions
- Confirm that the project has delivered what is defined in the Project Product Description, and that the acceptance criteria have been met
- Seek approval to give notice to corporate or programme management that resources can be (or are about to be) released
Diagram 2 shows the responsibilities for this activity.
© Crown copyright 2005 Reproduced under licence from OGC


Diagram 2
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.