Any dependencies between activities (and products) should also be identified.
There are two types of dependency: internal and external. An example of an internal dependency is that activity C cannot start until activities A and B have been completed.
External dependencies may, for example, be:
The delivery of a product required by this project from another project The provision of a purchase order by the user A decision from programme management.