Any project must have a decision maker and someone to carry out the project planning.
There must be a plan for the initiation work and the appointment of the Executive and the Project Management is a prerequisite.
The objectives are:
There must be a Project Mandate in existence first.
This indicates the size, type and complexity of the project.
It should show any political and business sensitivity.
It may include a draft Project Plan from earlier work.
The time frame will help in judging the availability of people for the key roles.
The steps needed will be:
Outlines, which can be tailored in discussions, for the Executive and Project Management roles are given in files ‘Executive.doc’ and ‘Project manager.doc’ in the product package.
This lies with corporate or programme management.
These are given in tabular form in the file ‘appointing an executive and a project manager.doc’ in the product package.
They are:
Management information | Usage | Explanation |
---|---|---|
Project Mandate | Input/update | The trigger for the project |
Agreed job descriptions for the Executive and Project Manager | Output | Basis for sign-up by the Executive and Project Manager |
Appointed Executive and Project Manager | Output | Job descriptions agreed |
These are given in tabular form in the file ‘appointing an executive and a project manager.doc’ in the product package.
If the size of the project warrants it the job descriptions should be signed and copies held with their line management and in the project files.
If it is considered that formal job descriptions are not necessary, for example the project is too small, the persons should at least understand the responsibilities.
If the project is part of a programme they will appoint the Executive and may influence the appointment of the Project Manager. The Executive will appoint the rest of the Project Board.