Just as the Work Package was accepted from the Project Manager, notification of its completion must be returned to the Project Manager.
The configuration management system used by the project may handle the return of the actual products of the Work Package.
The essence of this sub-process is that the Team Manager must ensure that the products are handed over correctly and advise the Project Manager that the handover has occurred.
The sub-process may trigger Authorising Work Package (CS1) for the next Work Package or may overlap with it.
This sub-process has three elements:
The methods of achieving these elements should have been defined as part of Work Package authorisation.
Before advising the Project Manger of the completion, the Team Manager should check that the Quality Log entries are complete for the product(s).
The Team Manager is responsible for this sub-process liaising with the Configuration Librarian.
Management information | Usage | Explanation |
---|---|---|
Completed Work Package | Input | Details of the work agreed with the Project Manager updated with actual information. |
Quality Log | Input | Confirmation of successful quality checks. |
Work Package | Output | Work Package ready for approval by the Project Manager |
These are given in tabular form in the file ‘MP3 delivering a work package.doc’ in the product package.
If the Work Package contains a number of products to be developed, they may be handed over to the project’s configuration management system as they are approved. This may imply a period of time before the Project Manager is notified that the whole Work Package has been completed.
The level of formality required will vary according to the project: formal when third parties are involved, informal when the Project Manager manages the work directly.