Make sure that initiation is not aimless and unstructured. Initiating the project and preparing the Project Plan will take time and consume resources.
The work should be planned and approved.
The Project Board now need to know what effort is required in preparing the Project Initiation Document.
Other aspects of the project already exist, for example, the Project Brief.
The objectives are:
The Project Initiation Document is an extension and refinement of the Project Brief with the addition of:
The initial Stage Plan needs to show the investigation and development of the extra information required, plus the development of the Project Brief into the format required for the Project Initiation Document.
The initiation stage should be short and inexpensive compared to the total project.
A stage structure for the project will be developed in this process.
At the end of initiation the Project Board will expect to see the Project Initiation Document and a detailed plan for the next stage.
This is because the extent of the commitment of the Project Board will only extend to the next stage.
If the project is part of a programme the existence of the initiation Stage Plan will give them due warning to prepare to review the Project Initiation Document.
The common Planning (PL) process is used to create the Stage Plan.
The Project Manager is responsible for planning the initiation stage.
Appointed Project Assurance and Project Support roles will assist.
Who ever is responsible for the business assurance will need to identify in the initiation Stage Plan how the Business Case and risk assessment will be checked.
Management information | Usage | Explanation |
---|---|---|
Project Approach | Input | This defines the method by which the work of the project will be carried out. This will have a bearing on the scale of work likely to be involved in initiating the project. |
Project Brief | Input | Details of the job to be done (plus any earlier planning work done) are contained in the Project Brief and will help to size the initiation stage. |
Risk Log | Update | Update with any new risks. |
Initiation Stage Plan | Output | An essential product to gain approval to perform project initiation. The plan for the initiation stage should be discussed informally with the Project Board. |
These are given in tabular form in the file ‘planning an initiation stage.doc’ in the product package.
Initiation stages are usually short, and as such, formal reporting may not be necessary to the Project Board if frequent communication exists.
For some small low risk projects it may not be necessary to produce a formal plan for the initiation stage.
The amount of start-up and initiation work, even for large and complex projects is dependent on what work has gone before.