Project management can end up being a daily ‘fire-fighting’ exercise.
Without suitable regular progress checks a project can quickly get out of control.
There must be a balance of forward planning and reacting to events.
There will often be a need to incorporate unplanned activities.
There must be a regular check on external events that could affect the project.
This sub-process brings together the information in Assessing Progress (CS2) and Examining Project Issues (CS4) and decides what actions should be taken next.
If the project is on track and within tolerance, the next action will be the submission of Reporting Highlights (CS6) to the Project Board and Authorising Work Package (CS1) for any subsequent work.
If corrective actions are needed, and the stage and project are predicted to stay within tolerance, the next sub-process will be Taking Corrective Action (CS7).
The Project Manager may seek advice and guidance from the Project Board about any Project Issues (Taking Corrective Action (CS7)) and should always do if the stage or project is predicted to go outside tolerance (Escalating Project Issues (CS8)). Reference to the Project Board may help other projects that could be affected.
This sub-process provides the means for a regular assessment of the stage status.
The process decides whether:
The first objective is to check periodically that the current stage is kept within the tolerances set down by the Project Board by:
If corrective action is needed, but the stage is forecast to stay within tolerance, the action can be taken by the Project Manager, as described in Taking Corrective Action (CS7).
The second objective of this sub-process is to review the project status, specifically:
To achieve these objectives various steps are required:
The Project Manager can use the Daily Log to note any of these checks that need to be done and many of the small actions that are needed after carrying the checks out.
The Project Manager is responsible for this sub-process, supported by any Project Support roles, including the Configuration Librarian and those with Project Assurance responsibilities. It may be necessary on occasion to consult Project Board members for guidance, especially with regard to Project Issues or resource shortfalls, or external even that may impact the Business Case or Risk Log.
Management information | Usage | Explanation |
---|---|---|
Issue Log | Input | This product will show the current situation regarding will Project Issues. These may be needed for reference when deciding on appropriate action to deal with them. |
Risk Log | Input | This product shows the current understanding of the problems and threats to the project. |
Project Plan | Input | Check to establish whether any stage problems (or potential change) would have an impact on the Project Plan. |
Product Checklist | Input | (If used) This shows the current actual and planned delivery dates for key products. |
Quality Log | Input | Assess the state of quality checking. |
Business Case | Input | This is checked for any impact from the current stage progress. |
Configuration Item Records | Input | These provide information on the current status of products. |
Stage Plan | Input | The Stage Plan, updated in Assessing Progress (CS2), provides the baseline against which progress and the meeting of stage tolerances are measured. |
Concession | Input | Decision by the Project Board to accept a Project Issue without corrective action. |
Plan deviation | Output | The information to be passed to Taking Corrective Action (CS7). |
Tolerance threat | Output | Trigger for an Exception Report. |
Stage status information | Input / Output | Information regarding the current progress of the project. This information goes forward to Reporting Highlights (CS6). |
Stage end notification | Output | Trigger for Managing Stage Boundaries (SB) (at the appropriate time near the stage end). |
Trigger for project end | Output | Trigger for Closing a Project (CP) (at the appropriate time near the final stage end). |
Work trigger | Output | Trigger for the issue of new Work Packages from Authorise Work Package (CS1). |
These are given in tabular form in the file ‘CS5 reviewing stage status.doc’ in the product package.
This sub-process will often occur concurrently with other processes.
It is a cyclic / iterative process.
The regularity of stage status review will depend on how closely control is needed and will be related to the length of the activities.
Smaller projects may be reviewed weekly whereas larger projects could be every 2 weeks or monthly.
Where activities bear greater importance, for example those on the critical path, they may need more frequent monitoring and control.
Any new or changed risks should be communicated to an existing programme for their impact on other projects.