Prince2 header
products page

PRINCE2 - Management of Risk part 4

Mapping the management of risk to the PRINCE2® processes

The requirement for risk management occurs at many stages during the various processes of a project.
It is not a one off activity. The diagram showing the processes where risk management [see ‘The Complete Risk Management package’] is used can be found in file ‘risk flow in the project.doc’ in the product package.

flow diagramflow diagram large

Preparing a Project Brief (SU4)

The Risk Log is required.
The Project Mandate (and the creation of the Project Approach) may have indicated some risks.
Risks such as, legislation change and introduction, cash flow problems and staff changes should be discussed as part of introducing the Project Brief.

Authorising Initiation (DP1)

The Project Board will look at the Risk Log to see if there is nay justification for initiating the project.
The Project Manager should have made Project Board members aware of the risks ahead of the meeting.

Refining the Business Case and Risks (IP3)

The Project Manager, as part of the preparation of the Project Initiation Document should revisit and review any risks.
The initial Project Plan will be created and which should identify many of the risks.

Authorising a Project (DP2)

The Project Board will have seen an updated Risk Log and reviewed the Business Case and hence assessed the status of the risk.
Based upon this they will approve or not the start of the project. Project Board members will own some of the risks.

Analysing risks (PL6)

As any plan progresses new risks may be identified, others modified and others eliminated.
The Risk Log should contain all information on identified risks and their status.
No plan should be updated and approved without first completing a review of the risks.
Naturally, tasks may be modified or added to account for the change in the presence of risk.

Updating the Risk Log (SB4)

This must be updated prior to the approval and start of the next stage.

Authorising a Stage or Exception Plan (DP3)

The Project Board must have the opportunity to assess the risk position prior to approval of the next stage.

Authorising Work Package (CS1)

During this activity the Team Manager might identify additional risks which require plan modification.
This may happen due to the use of new technology or a need to source specialised skills and equipment.

Accepting a Work Package (MP1)

The Team Manager will produce a plan for the implementation of the Work Packages which in turn raise possible risk issues.

Examining Project Issues (CS4)

Assessment of a Project Issue may introduce an new risk of modify an existing one beyond acceptable boundaries.

Reviewing Stage Status (CS5)

Here the Project Manager (with Project Assurance personnel) examines risk changes and other signs. This will be accomplished by reference to a variety of reports, such as, the Stage Plan (containing the latest actual data), the Project Plan, the Business Case, any open Project Issue, the tolerance status and the Risk Log.

Escalating Project Issues (CS8)

Apart from Project Issues, a risk change may cause the Project Manager to raise an Exception Report to the Project Board.

Reporting Highlights (CS6)

This provides an opportunity for the Project Manager to bring key aspects of risk to the attention of the Project Board.
These could be new risks, risks that no longer exist and a reminder of the risks owned by members of the Project Board.

Giving Ad Hoc Direction (DP4)

The Exception Report allows the Project Manager to bring exceptions to the attention of the Project Board.
Based upon this information the Project Board can provide necessary advice to indicate a direction to take.
This might involve project closure, the request of an Exception Plan or the removal of an obstacle.

The Project Manager will usually already be in communication with the Project Board and the meeting will help to ratify any decision making.

Identifying Follow-on Actions (CP2)

When the project is complete the product may still bear certain risk issues, during its operational life, which will be important to those involved in support.
These risks should be recorded in the Follow-on Action Recommendations.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.