If there is any unfinished business at the end of the project, it should be formally documented and passed to those who have the authority and responsibility to take action.
Most of the input will be those items on the Issue Log that were held back by the Project Board.
The output is submitted to the Project Board as Follow-on Action Recommendations.
The aims of this sub-process are to:
A number of actions may be required after the project.
The input will come mainly from those Project Issues that were put into ‘pending’ status by the Project Board during the project.
The Risk Log may also contain risks that may affect the product in its useful life.
All unfinished work is documented in Follow-on Action Recommendations.
Many project schedules should be re-examined after a period of use to check on their quality, effectiveness in use and achievement of benefits.
Examination of the updated Business Case will identify whether there are any expected benefits whose achievement cannot be measured until the product has been in use for some time. If this is the case, a recommendation date and plan should be made for a post-project review, the benefits to be measured at that time and the measurements too be applied.
These benefits should have been defined in the Business Case.
It is not a project activity to produce the post-project review, only to plan it.
In summary, the post-project review is to assess achievement of the benefits claimed in the Business Case.
The following questions are a sample:
The Post-Project Review Plan will make use of the information contained in the Business Case.
The Product Description is given in file ‘Business case.doc’ in the product package.
This should have stated how the achievement of benefits was to be measured.
The plan should be defining:
The Project Manager is responsible for this sub-process.
Management information | Usage | Explanation |
---|---|---|
Issue Log | Input | Unactioned Project Issues will form the basis of any Follow-on Action Recommendations. |
Business Case | Input | This will reveal benefits whose achievement cannot be measured immediately and will therefore need a post-project review. |
Risk Log | Input | Check for any risk to the operational use of the need product(s). |
Post-Project Review Plan | Output | Suggested plan for a post-project review for ratification by the Project Board. |
Follow-on Action Recommendations | Output | Recommendations for further work, which the Project Board must direct to the appropriate audience for attention. |
These are given in tabular form in the file ‘CP2 identifying follow-on actions.doc’ in the product package.
Arrangements for any post-project review should be discussed informally with the Project Board before making any recommendation so as to avoid any disagreement in the subsequent sub-process, 'Confirming Project Closure (DP5)'.
The date for the review should be set as soon after the project closes as would allow adequate assessment.
The quality of a product may have appeared fine during testing, but is it sill good after a period in the working environment?
Also, where some benefits will take much longer to come to fruition, it is worth considering a recommendation to the Project Board that these are the subjects of another, later post-project reviews.
Dependent on the type of project product, there may be contractual issues to be resolved for the operational and maintenance support of the products.
A copy of the recommended follow-on actions should always be sent to the operational support group to keep it informed.
Where the project is part of a programme, the Project Board’s recommendation to close the project should be reviewed by programme management in the light of the list of follow-on action recommended.
If the project is part of a programme, the follow-on actions should be assigned by programme management, where appropriate.