A generic agenda for Project Board reviews was introduced in ‘Progress control’ under ‘Ensure effective decision making’ in the section covering ‘Project Board duties and behaviours’.
The specific implementation suggested for authorizing initiation is outlined below.
Suggested Project Board agenda for authorizing initiation| Look back: | Review the background to the project and the Project Brief |
| Look forward: | Preview the Initiation Stage Plan |
| Assess overall project viability: | Review the outline Business Case and key issues/risks |
| Make a decision: | Authorize the initiation stage to commence (by approving the Initiation Stage Plan and Project Brief). |
All references above are in Directing Successful Projects with PRINCE2® unless stated otherwise.