A generic agenda for Project Board reviews was introduced in the section covering ‘Project Board duties and behaviours’ (see ‘Progress control’ under ‘Ensure effective decision making’).
The specific implementation suggested for confirming project closure is outlined blow.
| Look back: | Review the End Project Report, Review the Lessons Report and actions |
| Look forward: | Review the Benefits Review Plan, Approve the follow-on action recommendations |
| Assess overall project viability: | Confirm the final costs and expected benefits in the Business Case |
| Make a decision: | Authorize project closure by approving a project closure notification. |
All references above are in Directing Successful Projects with PRINCE2® unless stated otherwise.