During the delivery stages, the Project Board should ‘manage by exception’.
Members will be kept up-to-date by Highlight Reports from the Project Manager.
These are designed to be concise, but they can contain as much information as the Project Board requires.
Be aware that too frequent or too lengthy reports may well constrain a busy Project Manager’s ability to lead and communicate.
Highlight Reports are intended for information only - to keep Project Board members in touch with progress and build confidence that the work is on track.
Nevertheless, they will often prompt questions in the minds of Project Board members:
Project Managers often complain about the time they have to spend on reporting, given the apparent lack of interest/response to the reports.
Responding to Highlight Reports provides evidence of a Project Board member’s interest in and commitment to the work - and their understanding of the framework of plans and controls.
There may also be some simple opportunities for Project Board members to provide valuable assistance at the working level.
Highlight Reports are often also used to communicate progress outside the project management team, e.g. to stakeholders and interested line managers.
This is an efficient way of avoiding the need for additional reports but it can encourage interventions or even direction from outside the project management team.
When this occurs it needs to be managed sensitively, both by the Project Manager and Project Board members.
The Project Manager should refer any suggested changes of approach or direction, or complaints about project progress, to the appropriate Project Board member (or to someone assigned a Project Assurance role).
Project Board members (and others with responsibilities in the project) should always make clear to other stakeholders how the project management team works and where accountabilities lie.
Exception ReportsIn contrast to Highlight Reports, Exception Reports always require a response from Project Board members.
They are alerts to the need for replanning.
In all likelihood the Project Manager will have consulted Project Board members informally about the contents beforehand.
Exception Reports are evidence of good project management - irrespective of any failings that may have caused the exception - especially if the report is constructive, with good options for corrective action.
What Project Board members want to know from an Exception Report is:
The Executive’s concern is that the exception is managed properly.
The Senior User will wish to know whether the exception resulted from user-related issues and, if so, how best to help resolve them and capture the lessons.
Similarly, the Senior Supplier will be concerned to resolve any specialist technical issues and ensure that related lessons are identified, recorded and analysed.
As always, Project Board members should make every effort to support the replanning exercise.
The Project Board can respond to an Exception Report in one of three ways:
If there is a series of manageable exceptions, the Project Board may need to reconsider the stage tolerances and provide the Project Manager with more discretion.