Project management header
products page

Risk management - Multiple probability branching

Multiple probability branching

multiple probability branchingmultiple probability branching

Following on from the complex branching seen previously [see multiple branching part 2], the above gives an example of an even more complex model in terms of branching.
Here, we now have 3 potential pathways with probabilities of 50%, 20% and 30%.

For simplicity we have just one task in each pathway each with a finish to finish link.

The spreadsheet deals with this example in a slightly more complex manner.
The spreadsheet for this ‘multiple branching’ example is shown next [see multiple probability branching part 2].